Van de Wetering has transported the turbine for Norway’s largest hydroelectric power plant!
A hydroelectric power plant is under construction in Lysebotn, Norway. This plant is being built inside a mountain, next to the existing Lysebotn 1 hydroelectric power plant. The project, called Lysebotn 2, will have a final capacity of 370 MW and will generate 1.5 terawatt-hours of electricity per year. This makes it Norway’s largest hydroelectric power plant!
For this massive project, Van de Wetering was tasked with transporting the so-called “snail”—the turbine through which the water flows. This turbine came from Spain. Because the construction site of the hydroelectric power plant was inaccessible to a special transport like this, the final leg of the journey had to be completed by boat, which produced some spectacular footage!
Details
OBJECT
Turbine
TRANSPORTATION TYPE
Special transport
TRANSPORTATION TIME
11 days
PICKUP LOCATION
Spain
DELIVERY LOCATION
Norway
DIMENSIONS
10 x 6.3 x 2.4 meter
WEIGHT
46 ton
TRUCK TYPE
Scania V8
SPECIAL FEATURES
Delivery by boat through the fjord
DATE
10-03-2016